Back to Top
picture of parish

Home

  
  
  
Rollup Image
Page Content
  
22/01/2016Re-Surfacing of Village Green Car Park

​Resurfacing will be taking place at the car park entrance over half term from Saturday 13th February to Sunday  21st  February. Whilst limited access to the car park will be available for some of this period, there will also be times when the entrance is completely out of action. We therefore recommend that no vehicles are left in the car park during the above period as they may be become blocked in.

  
18/01/2016Latest Information

'Please note the Trinity to Gorey Section 3 Resurfacing works are due to re-start on Tuesday 19th January following a delay which has been caused by the requirement to close a section La Route de la Cote due a landslip which occurred to a property near Jeffreys Leap.

Works will be undertaken under road closed with working hours of 08.15 to 18.00, Monday to Friday. Extent of Phase 1 of the works are indicated on the attached image with the proposed diversion route clearly indicated.
If youy wish to discuss any of the above or have any further issues pleased do not hesitate to contact a member of Pallot Tarmac on either:
07829 849 487
or
07700 706 193

Steve Brown (Site Manager)

  
13/01/2016Road works re-commence 18th January: due to complete mid-March

STOP PRESS:  Due to the land slip between Gorey and Anne Port the contractors are making alternative arrangements.  Please see press announcements for up-to-date information, but current information is that work will now commence Monday, 18th January 

The follwoing message has been received by the contractors:-

As you may be aware there has been a land slip on La Route de la Cote which has resulted in the need to close this road to all traffic.

La Route de la Cote was due to be used as the part of the main diversion for the re-surfacing works project which was to commence on 12.01.16. Given the fact that the road is currently closed it has been decided that the we will delay implementing road closures on Le Mont Gabard/Le Grande Route de Faldouet until the 18.01.16.

To minimise disruption to the programme and to attempt to ensure the original completion date is achieved we will be commence works on Le Mont Gabard/Le Grande Route de Faldouet under lane closure. Please note, lane closure will only be in place for the proposed working hours of the scheme i.e. 08.15 – 18.00.

We apologise for any inconvenience in advance and we will endeavour to keep you up to date with our progress.

~~~

Please be aware that Section 3 of the Trinity to Gorey resurfacing project will start on 12th  18th January and is expected to be complete by mid-March.  The project has been split into 2 Phases which are detailed further as follows:

Phase 1 will commence at the junction of Le Mont de Gouray and Le Mont de Gabard and continue north to Ransoms Garden Centre on La Grande Route de Faldouet.  Works will be undertaken under road and lane closure where required.

On completion of Phase 1 works will commence on Phase 2 which will be from Ransoms Garden Centre  and continue northwards to approximately 80 metres south of the junction with Rue des Bassacres. 

 

Phase 1  will commemce on Tuesday, 12th January and we anticipate will be completed early February 2016 (subject to weather).  The working hours for road closures will be 8.15am to 6.00pm Monday to Friday. Please note that works will be a requirement to work one Sunday during the Phase 1 construction period. The date will be confirmed in a future letter drop.

Phase 2 will commence in early February (upon completion of Phase 1) with an anticipated completion date of mid-March 2016.

Further letter drops will be delivered prior to the commencement of each phase, indicating timing and extent of the next phase.  Should there be any changes to the programme these will be highlighted in future letter drops.

 For information relating to buses and temporary bus stops, please visit the Liberty Bus website.  www.libertybus.je

If you  have any concerns regarding the project, access arrangements, or any issues witht the works or traffic management, please contct our Safety and Management Officer on 07829 849487 during working hours.

Further information on the scheme can be found on the States of Jersey webpage: www.gov.je/travel/roads

Pallot Tarmac Ltd and Transport and Technical Services apologise in advance for any inconvenience that these essentiall highway mainteneance works may cause.

 

Pallot Tarmac

Site Manager

1 - 3Next
  
  
Rollup Image
  
  
196St Martin's W. I.
15/02/2016Canasta afternoon 2:00p.m. till 5:00p.m. in the Public Hall
175Whist Drive
16/02/2016Provisional date to be confirmed
106St Martin's Flower Club
02/03/2016St Martin's Flower Club meeting commences at 2:30p.m.
  
  
  
Rollup Image
Page Content
  
22/01/2016Re-Surfacing of Village Green Car Park

​Resurfacing will be taking place at the car park entrance over half term from Saturday 13th February to Sunday  21st  February. Whilst limited access to the car park will be available for some of this period, there will also be times when the entrance is completely out of action. We therefore recommend that no vehicles are left in the car park during the above period as they may be become blocked in.

  
18/01/2016Latest Information

'Please note the Trinity to Gorey Section 3 Resurfacing works are due to re-start on Tuesday 19th January following a delay which has been caused by the requirement to close a section La Route de la Cote due a landslip which occurred to a property near Jeffreys Leap.

Works will be undertaken under road closed with working hours of 08.15 to 18.00, Monday to Friday. Extent of Phase 1 of the works are indicated on the attached image with the proposed diversion route clearly indicated.
If youy wish to discuss any of the above or have any further issues pleased do not hesitate to contact a member of Pallot Tarmac on either:
07829 849 487
or
07700 706 193

Steve Brown (Site Manager)

  
13/01/2016Road works re-commence 18th January: due to complete mid-March

STOP PRESS:  Due to the land slip between Gorey and Anne Port the contractors are making alternative arrangements.  Please see press announcements for up-to-date information, but current information is that work will now commence Monday, 18th January 

The follwoing message has been received by the contractors:-

As you may be aware there has been a land slip on La Route de la Cote which has resulted in the need to close this road to all traffic.

La Route de la Cote was due to be used as the part of the main diversion for the re-surfacing works project which was to commence on 12.01.16. Given the fact that the road is currently closed it has been decided that the we will delay implementing road closures on Le Mont Gabard/Le Grande Route de Faldouet until the 18.01.16.

To minimise disruption to the programme and to attempt to ensure the original completion date is achieved we will be commence works on Le Mont Gabard/Le Grande Route de Faldouet under lane closure. Please note, lane closure will only be in place for the proposed working hours of the scheme i.e. 08.15 – 18.00.

We apologise for any inconvenience in advance and we will endeavour to keep you up to date with our progress.

~~~

Please be aware that Section 3 of the Trinity to Gorey resurfacing project will start on 12th  18th January and is expected to be complete by mid-March.  The project has been split into 2 Phases which are detailed further as follows:

Phase 1 will commence at the junction of Le Mont de Gouray and Le Mont de Gabard and continue north to Ransoms Garden Centre on La Grande Route de Faldouet.  Works will be undertaken under road and lane closure where required.

On completion of Phase 1 works will commence on Phase 2 which will be from Ransoms Garden Centre  and continue northwards to approximately 80 metres south of the junction with Rue des Bassacres. 

 

Phase 1  will commemce on Tuesday, 12th January and we anticipate will be completed early February 2016 (subject to weather).  The working hours for road closures will be 8.15am to 6.00pm Monday to Friday. Please note that works will be a requirement to work one Sunday during the Phase 1 construction period. The date will be confirmed in a future letter drop.

Phase 2 will commence in early February (upon completion of Phase 1) with an anticipated completion date of mid-March 2016.

Further letter drops will be delivered prior to the commencement of each phase, indicating timing and extent of the next phase.  Should there be any changes to the programme these will be highlighted in future letter drops.

 For information relating to buses and temporary bus stops, please visit the Liberty Bus website.  www.libertybus.je

If you  have any concerns regarding the project, access arrangements, or any issues witht the works or traffic management, please contct our Safety and Management Officer on 07829 849487 during working hours.

Further information on the scheme can be found on the States of Jersey webpage: www.gov.je/travel/roads

Pallot Tarmac Ltd and Transport and Technical Services apologise in advance for any inconvenience that these essentiall highway mainteneance works may cause.

 

Pallot Tarmac

Site Manager

1 - 3Next
  
  
Rollup Image
  
  
196St Martin's W. I.
15/02/2016Canasta afternoon 2:00p.m. till 5:00p.m. in the Public Hall
175Whist Drive
16/02/2016Provisional date to be confirmed
106St Martin's Flower Club
02/03/2016St Martin's Flower Club meeting commences at 2:30p.m.